# Scope creep

Also known as: Requirement creep, Feature creep, Scope expansion

## What is Scope creep?

Uncontrolled growth in project requirements or activities beyond what was originally defined in the SOW.

## How does Scope creep work?

Scope creep is the main cause of margin erosion in Fixed Price projects: small additional client requests, accepted out of courtesy or haste, pile up until effort explodes without any price increase.

Defense rests on three elements: a detailed SOW precisely describing what is in and out of scope, a formal change-request process that turns every new request into a contract amendment or upsell, and a PSA that alerts the PM when delivered hours exceed baseline. Industry studies estimate that scope creep cuts average margin by 10-20% in projects without structured change management.

The requests that cause the most damage are the ones too small to refuse. A half-day of analysis, one extra review cycle, a report in a different format: none of them justifies the friction of a change request, and twelve of them consume a fortnight nobody planned for. Counting them, rather than pricing each one, is usually what makes the pattern arguable with the client.

Detecting the drift early is mostly a matter of watching two signals that appear long before the budget does: hours booked against tasks that were not in the plan, and milestones re-baselined more than once. Both are visible in week three of a slippage, when renegotiating scope is still a normal conversation rather than an escalation.

## A practical example of Scope creep

An integration sold at 150k€ ends at 220 actual person-days vs 180 estimated: 22% scope creep, margin dropped from 32% to 12%.